How often is a LOLER inspection needed? 6 or 12 months, by machine

Published

Six months for anything that lifts people and for all lifting accessories. Twelve months for other lifting equipment. This guide sets out which of your machines fall where, when an examination is needed sooner, who can do it and how long to keep the reports.

The short answer

6 months

Equipment used to lift people, and every lifting accessory (chains, slings, shackles, hooks, eyebolts).

12 months

All other lifting equipment: telehandlers, forklifts, cranes and hoists that lift loads, not people.

These are the longest gaps the regulations allow by default. A competent person can write an examination scheme with different intervals, and they are often shorter for hard-worked equipment.

Track every machine's LOLER date, 6 or 12 months, and get an email before it is due. Free.

See How

"Inspection" or "thorough examination"?

Most people say "LOLER inspection". The regulations call it a thorough examination: a systematic and detailed examination of the equipment and its safety-critical parts, carried out by a competent person who then writes a report. That is the 6 or 12 monthly one this guide is about.

An inspection in LOLER means something lighter: the checks made between thorough examinations, such as an operator's pre-use or weekly check. Both matter, but only the thorough examination has the fixed intervals.

Which interval for which machine

The default interval for common fleet, plant and farm equipment, worked out from the two rules above.

EquipmentAt least everyWhy
Telehandler lifting loads on forks or a bucket12 monthsLifting equipment that does not lift people.
Telehandler used with a purpose-made work platform to lift people6 monthsAnything used to lift people is 6 months. See the warning below the table.
Forklift truck12 monthsThe chains, forks, mast, cylinders and fork attachments are what is examined.
Excavator used for lifting (slinging a load from its lifting point)12 monthsIt must also be permitted by the maker and have a marked lifting point.
Lorry loader crane12 monthsLifting equipment that does not lift people.
Tractor front loader12 monthsHSE names foreloaders as lifting equipment that needs a thorough examination.
MEWP, cherry picker or scissor lift6 monthsIt lifts people.
Workshop vehicle lift, engine crane, chain block or hoist12 monthsLifting equipment that does not lift people.
Chains, slings, shackles, hooks and eyebolts6 monthsAll lifting accessories are 6 months.

Lifting people. HSE says people should only be raised on equipment designed for it. Another machine may be used only in exceptional circumstances, with a purpose-made platform that is properly attached. Nobody should ever be lifted in a telehandler bucket, in a potato box or on the forks. A tractor front loader is for loads, not people.

Not lifting equipment under LOLER: a tractor's three-point linkage when it lifts an implement made for it, a simple pallet truck that only raises the load just clear of the ground, and most conveyors. Pallets and skips are normally treated as part of the load and do not need a thorough examination. All of these still have to be kept safe under PUWER.

When an examination is needed sooner

The 6 and 12 month dates are not the only trigger. Lifting equipment must also be thoroughly examined:

  • Before it is first used, unless it is new, came with a Declaration of Conformity made less than 12 months ago and was not assembled on site.
  • After installation or assembly, before use at each location, where its safety depends on how it is installed (a tower crane, for example).
  • After exceptional circumstances that could affect its safety: damage or a failure, a long period out of use, or a major change such as a modification or the repair or replacement of a critical part.

Hiring a machine in, or buying one second-hand? It must come with evidence of its last thorough examination. Ask for the current report before it goes to work.

Who can do it, and why a service does not count

The examination has to be done by a competent person: someone with the practical and theoretical knowledge and experience of that equipment to find defects and judge what they mean for its safety. In practice that is usually an engineer surveyor from an insurer or an inspection company.

It can be someone you employ, as long as they are independent and impartial enough to make the call. It should not be the person who carries out the routine maintenance, because they would be assessing their own work.

A service is not a thorough examination. Servicing keeps the machine working; the examination checks it is safe to keep using. You need both, and the examination date does not move because the machine was serviced last month.

What the report must say, and what to do about defects

The written report has to include the date of the examination, the date the next one is due and any defect that is, or could become, a danger to people. That "next due" date is the one to diary: it may be sooner than 6 or 12 months if the examiner decides so.

If a serious defect is found you must be told straight away, and the equipment must not be used until it is put right. The examiner also sends a copy of the report to the enforcing authority. For a lesser defect the report gives a date by which it must be remedied; fix it by then or stop using the equipment.

How long to keep LOLER reports

RecordKeep it
The examination before a machine is first usedFor as long as you use the machine
The examination before a lifting accessory is first used2 years after the report is made
An examination after installation or assembly on a siteUntil you stop using it at that place
The regular 6 or 12 monthly examinationsUntil the next report is made, or 2 years, whichever is later
The Declaration of Conformity that came with the machineFor as long as you operate the machine

Reports do not have to be on paper. They can be kept electronically if they are protected from being changed and you can produce a copy when an inspector asks, or when the machine is hired out or sold.

Northern Ireland

Northern Ireland has its own regulations, the Lifting Operations and Lifting Equipment Regulations (Northern Ireland) 1999, enforced by HSENI. The intervals are the same as in Great Britain: at least every 6 months for equipment lifting people and for lifting accessories, at least every 12 months for other lifting equipment, or in line with an examination scheme.

Keeping on top of the dates

The examinations themselves are the easy part: the examiner turns up and does them. What goes wrong is the date. A telehandler is on 12 months, the man basket and the chains are on 6, a hired machine arrives with its own date, and one slips past.

In FleetBolt each machine has its own LOLER date and its own interval, 6 or 12 months. The Key dates page lists every one in red, amber or green, an email goes out 30, 14 and 7 days before it is due, and the examiner's report can be stored against the machine. Recording the examination moves the date on.

LOLER and key date tracking in FleetBolt

Common questions